You are at:Home»Energy»Years-long wait for permits blocking European wind farms, industry says –
Energy

Years-long wait for permits blocking European wind farms, industry says –

July 8, 20242 Mins Read
Share Facebook Twitter Pinterest LinkedIn Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email
OLOGI Ad 2


Hundreds of gigawatts of wind energy projects are waiting for permits to connect to Europe’s power grid, a backlog that threatens to slow the shift to green energy, industry association WindEurope said on Friday (5 July).

Why it’s important

Gaining access to the power grid is now the biggest hurdle to Europe’s expansion of renewable energy, WindEurope said.

With Europe’s power networks upgraded too slowly to absorb more capacity, and sluggish grid-permitting procedures in many countries, some projects face waiting times of up to nine years to receive a permit.

“The system is clogged up – and holding back hundreds of gigawatts of wind farms,” WindEurope CEO Giles Dickson said.

By the numbers

European wind energy projects with a total of more than 500 gigawatts of potential capacity are waiting for an answer to their requests for grid connections, across countries including France, Germany, Ireland, Poland and Spain, the data published on Friday showed.

Italy and the UK each have more than 100 GW of potential projects awaiting grid connection assessments.

The EU has a target to derive 42.5% of its energy from renewable sources by 2030. That implies expanding wind power capacity to 425 GW by 2030, up from 220 GW today.

What’s next

The queue of wind projects is at various stages and not all are likely to be built. For example, some are competing against one another for subsidies, WindEurope said.

Part of the problem is that projects are assessed on a “first come, first served” basis when they apply, meaning the most mature projects – those most likely to go ahead – cannot jump the queue.

Europe’s energy industry has urged governments to spur investments in expanding grids to prepare for a bigger influx of renewable power, and filter applications so that projects that are ready to launch receive permits fast.

Read more with Euractiv

Von der Leyen urged to shield EU hydrogen industry, with focus on electrolyser producers

Subscribe now to our newsletter EU Elections Decoded

Energy News

As energy costs rise, some states back off ambitious climate goals

U.S. and Iran could meet in Pakistan for peace talks next week: MS NOW

GFL Environmental to Buy Secure Waste Infrastructure

Oil prices near $100 as U.S. blockades Iran ports after talks fail

Banks News

FCA sets out plans for industry to compensate 12.1 million for car finance

Lake Shore Bancorp Lags Rivals Across Key Metrics

Scott Bessent Banking Plan April 15: Citizenship Data Order

AI Minister to meet with Anthropic on cyber risks posed by Mythos AI model

Real Estate News

Inside Kardashian Brand Guru Emma Grede’s $70 Million Property Empire

Realty One, The Agency settle in homebuyer commissions case

2 Texas associations to merge; MLS alliance expands in Florida

Pristine A. Quincy Jones House Built for Utopian L.A. Community Lists for

© 2026 finmar.news

Type above and press Enter to search. Press Esc to cancel.